Project Summary |
Sample Maps |
|
Client: Williams Pipeline Company Project: Texas Eastman Project Location: Texas Status: Williams Pipeline has requested L.W. Survey to perform survey and drafting services on 76 miles of pipeline known as the Texas Eastman Project. This particular project begins on the South side of Houston, Texas and extends in a Southerly direction 76 miles, this survey is to be known as a purchase of inventory survey. The project will consist of locating a single pipeline and defining all points of interest, topographical features and pipeline direction/P.I.s. The pipeline will be located with a metrotech and RTK will be the method of centerline survey, with the exception of areas where RTK cannot be used, Laser EDM will be used. This project started May 1, 1999 and was completed June 21, 1999.
|
|